2026-07-06
The week in data — 2026-07-06 (numbers-only edition)
Numbers-only edition: the deterministic weekly context, published without narration. Every line is generated from the committed data.
This issue was published without narration — no LLM was available to the weekly action. Every line below comes deterministically from the committed data; a narrated issue resumes when the key is restored.
META
Today (digest date): 2026-07-06
Digest issue number: 3
Diff baseline: commit that published 2026-07-01.md [640bafbec804]
ABOUT LLI-RADAR (standing facts, primary-source verified)
lli-radar
The public record of ERCOT's large-load interconnection queue, assembled from primary sources nobody else maintains.
ERCOT tracks ~466 GW of requested large load (~90% data centers) but publishes the queue only as aggregate MW in PDF slide decks tied to TAC/LLWG meetings — 8,926 MW approved to energize, only 3,900 MW observed operating, a 0.8% funnel from request to reality (June 2026 LLI status update). There is no machine-readable time series, no consolidated regulatory feed, and ERCOT's own Large Load Portal (targeted end-2026) will be customer-facing, not public. lli-radar fills that gap with three things:
- The queue time series — every LLI Queue Status deck since October 2022, extracted into one clean dataset (
data/queue_timeseries.csv). - The regulatory radar — Batch Zero milestone countdown (PGRR145/NPRR1325), PUCT docket filing feeds (58481, 59142, and the SB 6 satellites), LLWG/TAC material watch.
- The weekly digest — what changed, in plain English, with the numbers injected from the data, not generated.
Everything is files in git. No database, no backend, no auth. The repo history is the audit trail.
BATCH ZERO CLOCK / UPCOMING DEADLINES (next 30 days flagged)
- 2026-07-11 (5 days away) [WITHIN 30 DAYS]: Recommended effective date for Batch Zero and WLPUN (PCLR effective upon system implementation). From the NPRR1325/PGRR145 issue pages. (status: scheduled)
- 2026-07-10 (4 days away) [WITHIN 30 DAYS]: ILLE submission deadline: study/dynamic-model data plus eligibility materials due to the interconnecting TSP/DSP. Missed means excluded from Batch Zero. Also the last day for legacy LLIS approvals under the current serial process. (status: scheduled)
- 2026-07-24 (18 days away) [WITHIN 30 DAYS]: TSP/DSP qualification packages due to ERCOT — attestations, disclosures, financial-security confirmations — plus PCLR Form W Part A (notarized, binding minimum LCP per study year) for projects electing the provisional pathway. (status: scheduled)
- 2026-08-07 (32 days away): ERCOT issues deficiency notifications on submitted qualification packages. Date is from the June 5 timeline deck, not the live ERCOT LLI page — lower confidence. (status: projected)
- 2026-08-31 (56 days away): Final inclusion cut — the Batch Zero study roster is fixed. Excluded projects wait for Batch 1 (potential case build June 2027). Date is from the June 5 timeline deck, not the live ERCOT LLI page — lower confidence. (status: projected)
- 2027-01-29 (207 days away): Batch Zero study results and MW allocation. Allocated MW reserved against restudy; the commitment gate (interconnection agreement plus financial commitments) converts allocation to firm. Date is projected from secondary sources (study results ~Jan 2027, IA execution ~Mar 2027) — ERCOT has not published a primary-source final-report date. (status: projected)
ERCOT DOCUMENTS (new/changed since baseline, from data/manifest.json)
- NEW document: Section 9: Large Load Additions at New or Modification of Existing Load Interconnection(s) (page: planning_guide_s9) https://www.ercot.com/files/docs/2011/04/28/09-070126.docx
- NEW document: Section 3: Regional Planning (page: planning_guide_s9) https://www.ercot.com/files/docs/2025/12/01/03-070126.docx
- NEW document: Section 5: Generator Interconnection or Modification (page: planning_guide_s9) https://www.ercot.com/files/docs/2025/12/01/05-070126.docx
- NEW document: Section 6: Data/Modeling (page: planning_guide_s9) https://www.ercot.com/files/docs/2025/12/01/06-070126.docx
- NEW document: Batch-Zero-Readiness-Weekly-Meeting-20260701 (page: llwg) https://www.ercot.com/files/docs/2026/07/01/Batch-Zero-Readiness-Weekly-Meeting-20260701.pptx
- NEW document: Batch_Zero_Readiness_FAQs_V3 (page: llwg) https://www.ercot.com/files/docs/2026/07/01/Batch_Zero_Readiness_FAQs_V3.xlsx
PUCT FILINGS (new since baseline, from data/filings/*.json)
No new PUCT filings since the baseline.
QUEUE TIME SERIES (data/queue_timeseries.csv, newest report vs prior)
Newest report_date: 2026-06-18; prior report_date: 2026-05-20
- Large Load Queue — Co-Located (latest snapshot 2026-06): 69708 MW
- Large Load Queue — Standalone (latest snapshot 2026-06): 396789 MW
- Large Load Queue — Total (latest snapshot 2026-06): 466497 MW
- No Studies Submitted: 257600 MW (prior 307700 MW, change -50100 MW)
- Under ERCOT Review: 151100 MW (prior 75400 MW, change +75700 MW)
- Section 9.4 Requirements Only: 11800 MW (prior 9300 MW, change +2500 MW)
- Section 9.4/9.5 Requirements Met: 37100 MW (prior 37100 MW, change +0 MW)
- A2E but not operational: 3200 MW (prior 2000 MW, change +1200 MW)
- Observed Energized: 5700 MW (prior 7100 MW, change -1400 MW)
- Total (GW) — full queue projection: 466500 MW (prior 438600 MW, change +27900 MW)
- Under ERCOT Review (studies in progress or complete): 151100 MW (prior 75400 MW, change +75700 MW)
- Section 9.4 Requirements Only (studies in progress or complete): 11800 MW (prior 9300 MW, change +2500 MW)
- Section 9.4/9.5 Requirements Met (studies in progress or complete): 37100 MW (prior 37100 MW, change +0 MW)
- A2E but not operational (studies in progress or complete): 3200 MW (prior 2000 MW, change +1200 MW)
- Observed Energized (studies in progress or complete): 5700 MW (prior 7100 MW, change -1400 MW)
- Total (GW) — studies in progress or complete: 208900 MW (prior 130800 MW, change +78100 MW)
- ERCOT Approvals — Section 9.4 (latest snapshot 2026-06): 11803 MW
- ERCOT Approvals — Section 9.4/9.5 (latest snapshot 2026-06): 37085 MW
- ERCOT Approvals — Approved to Energize (latest snapshot 2026-06): 8926 MW
- ERCOT Approvals — Total (latest snapshot 2026-06): 57814 MW
- Loads Approved to Energize — Observed Non-Simultaneous Peak Load (latest 2026-06): 3900 MW
- Loads Approved to Energize — Remaining Approved to Energize (latest 2026-06): 5026 MW
- Loads Approved to Energize — Total Approved to Energize (latest 2026-06): 8926 MW
- Loads Approved to Energize — Observed Simultaneous Peak Load (latest 2026-06): 3675 MW
- Loads Approved to Energize — Remaining Approved to Energize Load (simultaneous chart, latest 2026-06): 5251 MW
- Loads Approved to Energize — Total (simultaneous chart, latest 2026-06): 8926 MW
- Batch Zero Tracking by Weather Zone (GWs) — (1) Base Load Eligible: 24900 MW
- Batch Zero Tracking by Weather Zone (GWs) — (2a) Studies Validated: 8700 MW
- Batch Zero Tracking by Weather Zone (GWs) — (2b) Potentially Invalid: 4200 MW
- Batch Zero Tracking by Weather Zone (GWs) — (2c) Under Review: 3000 MW
- Batch Zero Tracking by Weather Zone (GWs) — (3) Studied/Base Eligible: 9600 MW
- Batch Zero Tracking by Weather Zone (GWs) — (4) One Study Complete: 46600 MW
- Batch Zero Tracking by Weather Zone (GWs) — (5) Path to Studied: 97200 MW
- Batch Zero Tracking by Weather Zone (GWs) — (6) Not Included: 287200 MW
- Batch Zero Tracking by Weather Zone (GWs) — Total (GW): 481400 MW