The public record of ERCOT's large-load queue

466 gigawatts are waiting.
3.9 are live.

Texas's tracked large-load queue has grown about 12.2× since 2022 — to roughly 466 GW, most of it data centers. Getting plugged in is another story.

§ 01

Requested is not built

Between a queue request and a running load sit studies, agreements, security postings, and transmission. The distance between these three numbers is the whole story.

Requested· tracked queue
~466GW
Approved to energize· cleared studies
8,926MW
1.9% of requested
Observed operating· energized load
3,900MW
0.8% of requested
One linear scale — the near-invisible bars are the point, not a rendering error. Tracked queue at Jun '26; approved-to-energize and observed-operating per the ERCOT LLI status update, June 2026.
§ 02

The line to plug into Texas

The tracked queue total, one point per ERCOT LLI Queue Status deck, since 2022.

Tracked large-load queue total, 38.1 GW (2022-09) → 466 GW (2026-06)0100200300400500GW2023202420252026+172 GW · 2026-0338.1 GW · 2022-09466GW2026-06 · 12.2×
Tracked queue total, one point per ERCOT LLI Queue Status deck (Sep 26, 2022 → Jun 18, 2026). Source URLs, SHA-256, and methodology on the Data page.
§ 03

The Batch Zero clock

Batch Zero replaces the serial study process with a single window: miss it and a project waits for Batch 1. Full table and fee math on the Batch Zero page.

Deficiency noticesAugust 7, 2026 · scheduled · source
T−5days
Final inclusion cutAugust 31, 2026 · projected
T−29days

Full Batch Zero clock